World’s longest expressway between Delhi and Mumbai to open in March 2023: All you need to know


Union Minister for Road Transport and Highways Nitin Gadkari on Friday concluded the two-day review of the work progress on the 1380-km eight-lane Delhi-Mumbai Expressway, which will reduce travel time between certain cities to 12-12.5 hours from 24 hours.


Gadkari toured Delhi, Haryana, Rajasthan, Madhya Pradesh and Gujarat over the two days to review progress of the project, being built at a cost of Rs 98,000 crore and scheduled to be completed by March 2023.


What is the Delhi-Mumbai expressway?

  • Cost: Rs 98,000 crore

  • Length: 1,380 km

  • Completion schedule: The first phase from Delhi-Jaipur (Dausa)-Lalsot and Vadodara-Ankleshwar is expected to be open to traffic by March 2022. The expressway is expected to be completed by March 2023.

  • The project was kickstarted in 2018 with the foundation stone being laid on March 9, 2019.

  • The expressway will feature a spur to Jewar Airport and Jawaharlal Nehru Port to Mumbai through a spur in Mumbai.

  • The expressway will improve connectivity to economic hubs like Jaipur, Kishangarh, Ajmer, Kota, Chittorgarh, Udaipur, Bhopal, Ujjain, Indore, Ahmedabad, Vadodara and Surat.

  • Out of the 1,380 km, contracts have been awarded for more than 1,200 km where work is under progress.

  • Over 15,000 hectares of land has been acquired across states for the construction of the Delhi-Mumbai expressway.


Read More at https://indianexpress.com/article/explained/mumbai-delhi-expressway-features-explained-7516029